IT – Equity Derivatives Trading Re-platform Update

As previously announced, Nasdaq Nordic Derivatives Markets will migrate the trading of Nordic equity derivatives, currently on the Genium INET platform to the new Nordic Derivates Trading System (NDTS) on February 21, 2022. Clearing of Nordic equity derivatives will continue in Genium INET after the trading re-platform.

 

Member Testing Weeks

The NDTS Pre-Production environment is now open for connectivity tests and logons. Trading activities can be tested during Member Testing weeks on December 20-22 and on January 3-11.

 

Until two weeks before go-live, Pre-Production OUCH ports will be using temporary passwords, whereafter the passwords will be updated to production passwords. 


December 20-22: Members will be able to logon and verify order management relevant to business.

January 3-11: Members will be able to logon and verify order management relevant to business. Specific MWAT scenarios will run during regular trading days for members to participate in.

 

Scheduled events in NDTS Pre-Production during January 3-5, 7, 10-11:

Time Scheduled Event
10:10 Intraday add in instrument
New strikes will be added be in the following option series: 
OMXS302CXXXX
OMXS302OYYYY
11:30-17:30 Regulatory suspension
Suspension of Ericsson.
Orders will be removed from all Ericsson instruments.
11:30-11:33
11:40-11:43
 
Volatility Auction "Circuit Breaker" 
Volatility Auction on OMXS302C Future. Orders & Quotes in OMXS302C will participate in “Volatility Auction”.
12:00-12:20 Performance
The aim is to test realistic but high load generated by Nasdaq. Members to continue production like trading.
12:30-12:40 Disturbance tests
Trading Halt on all Markets a so called “Technical Halt”. All orders and quotes are cancelled.
12:45 Failover
Intra Site Failover. Failover from customers primary port to customers failover port. Verify that cancel on disconnect works according to your specific setup.

 

 

 

Market Wide Acceptance Test (MWAT)

To prepare for production launch, two Market Wide Acceptance Tests (with backup dates) will be arranged in the NDTS Pre-Production environment in January. It is mandatory to participate in at least one of the MWATs:

  • MWAT Registration: January 7
  • MWAT 1: Saturday January 22 (10:30-13:00 CET)
  • MWAT 2: Wednesday January 26 (17:30-20:00 CET)
  • Backup: Saturday January 29 (10:30-13:00 CET)
  • Backup: Monday January 31 (17:30-20:00 CET)

The detailed schedules for MWAT 1 and MWAT 2 can be found below.


MWAT 1 - Saturday January 22:

Time Trading State Test activity
09:00-   Connect your applications
10:30   MWAT Starts
10:30-11:00 Pre Open Cancel order
10:45-11:00 Pre-Trading Enter & cancel order (for applicable products)
11:00-11:05 Opening Auction Enter & cancel order (for applicable products)
11:05-12:55 Continuous Trading
 
Order Management:
Enter order types relevant to the members business and validate the result.
 
Example of insert order types & order management:
-Place, update and cancel orders 
-Place, update and cancel Market Maker Quotes
 
Register manual trade reports: 
Submit trade reports relevant to the members business and validate the result.
 
Market Data
Verify Market data information.
12:55-13:00 Closing Auction Post close  
13:00 Close
 
MWAT Ends
Please fill in and send test report

 

Scheduled Events – MWAT 1 January 22:

Time Scheduled Event
11:10 Intraday add in instrument
New strikes will be added be in the following option series: 
OMXS302CXXXX
OMXS302OYYYY
11:30-13:00 Regulatory suspension
Suspension of Ericsson.
Orders will be removed from all Ericsson instruments.
11:30-11:33
11:40-11:43
 
Volatility Auction "Circuit Breaker" 
Volatility Auction on OMXS302C Future. Orders & Quotes in OMXS302C will participate in “Volatility Auction”.
12:00-12:20 Performance
The aim is to test realistic but high load generated by Nasdaq. Members to continue production like trading.
12:30-12:40 Disturbance tests
Trading Halt on all Markets a so called “Technical Halt”. All orders and quotes are cancelled.
12:45 Failover
Intra Site Failover. Failover from customers primary port to customers failover port. Verify that cancel on disconnect works according to your specific setup.

 

MWAT 2 - Wednesday January 26:

Time Trading State Test activity
16:00-   Connect your applications
17:30   MWAT Starts
17:30-18:00 Pre Open Cancel order
17:45-18:00 Pre-Trading Enter & cancel order (for applicable products)
18:00-18:05 Opening Auction Enter & cancel order (for applicable products)
18:05-19:55 Continuous Trading
 
Order Management:
Enter order types relevant to the members business and validate the result.
 
Example of insert order types & order management:
-Place, update and cancel orders 
-Place, update and cancel Market Maker Quotes
 
Register manual trade reports: 
Submit trade reports relevant to the members business and validate the result.
 
Market Data
Verify Market data information.
19:55-20:00 Closing Auction Post close
 
 
20:00 Close
 
MWAT Ends
Please fill in and send test report

 

Scheduled Events – MWAT 2 January 26:

Time Scheduled Event
18:10 Intraday add in instrument
New strikes will be added be in the following option series: 
OMXS302CXXXX
OMXS302OYYYY
18:30-20:00 Regulatory suspension
Suspension of Ericsson.
Orders will be removed from all Ericsson instruments.
18:30-18:33
18:40-18:43
 
Volatility Auction "Circuit Breaker" 
Volatility Auction on OMXS302C Future. Orders & Quotes in OMXS302C will participate in “Volatility Auction”.
19:00-19:20 Performance
The aim is to test realistic but high load generated by Nasdaq. Members to continue production like trading.
19:30-19:40 Disturbance tests
Trading Halt on all Markets a so called “Technical Halt”. All orders and quotes are cancelled.
19:45 Failover
Intra Site Failover. Failover from customers primary port to customers failover port. Verify that cancel on disconnect works according to your specific setup.

 

 

 

Throttle Limits for NDTS

Throttle Limits defining maximum allowed number of orders/quotes per second on OUCH and FIX ports can be found on the port request forms in Member Portal.


User Configuration Changes in Genium INET

The existing user types that are currently used for equity derivatives in Genium INET will be changed on February 21, 2022. Note that if a user is currently configured to have access to both equity derivatives and fixed income derivatives instruments, these users will be reconfigured to only allow fixed income derivatives and continue to be billed as before.

Trader & Marker Maker OMnet Users

Trading users (EX/EXWHB) & Market Maker users (MM/MMP) will be discontinued and not used for equity derivatives.

Trading Workstation Users

All Trading Workstation (TW) users will be discontinued for equity derivatives members.

Price and Trade Information OMnet Users

Price Information users (PI) will be discontinued and not used for equity derivatives as no market data (from Genium INET) will be provided for equity derivatives. Price and Trade Information users (PTI) will be reconfigured to only provide dedicated trade information, but not market data for equity derivatives.

The changes will be implemented on February 21, 2022. To verify your current user list please reach out to Member & Account Configuration team
mac@nasdaq.com.


Re-platforming webpage

Latest information on the migration to the new Nordic Equity Derivatives Trading System is available on the re-platforming webpage: https://www.nasdaq.com/solutions/nordic-equity-derivatives-platform-migration


Further information

For technical questions, please contact:

Technical Support
E-mail: 
technicalsupport@nasdaq.com
Tel: +46 8 405 6750

For questions regarding this IT-Notice, please contact:

Anders Bergström
E-mail: 
anders.bergstrom@nasdaq.com
Tel: +46 8 405 7364

or

Riitta Pesiö
E-mail: 
riitta.pesio@nasdaq.com
Tel: +46S 8 405 6437

 

IT - Equity Derivatives Trading Replatform Update_2021-12-17 003.pdf