As previously communicated, Nasdaq Nordic (Nasdaq Copenhagen A/S, Nasdaq Helsinki Ltd, Nasdaq Iceland hf., Nasdaq Oslo ASA and Nasdaq Stockholm AB), Nasdaq Baltic (Nasdaq Tallinn AS, Nasdaq Riga AS and AB Nasdaq Vilnius), Nasdaq Clearing AB and Nasdaq CSD SE will relocate the secondary data center from PORT to STOCKHOLM SOUTH (Equinix SK2) during Q2–Q3, 2025. The relocation will impact all trading, clearing, market data and Nasdaq CSD production systems. The planned changes are subject, where relevant, to regulatory consent.
Updated Time Schedule
The secondary data center relocation will be carried out using a phased approach. Updated time schedule for the relocation activities is as follows:
Relocation activities are expected to be completed on the following days: April 26 - Genium INET; May 10 - INET Nordic; May 17 - GCF; May 24 - NDTS. In connection with these dates, a connectivity verification test will be arranged with the possibility to perform a login test to the new failover IP addresses. The planned changes are subject, where relevant, to regulatory consent.
Connectivity testing
Test schedule – Genium INET
Connectivity testing for Genium INET will be available according to the following schedule:
Testing dates | Testing hours | Testing method | Comments |
March 3-7 | 12:00-18:00 CET | Telnet |
All protocols available for Telnet testing (Exception: TradeGuard). Possible to join ITCH and AMD Multicasts and receive heartbeats. |
March 8 | 10:00-14:00 CET | Login | API login available |
March 9-16 | Testing not available | Testing not available | Testing not available |
March 17-21 | 12:00-18:00 CET | Telnet |
All protocols available for Telnet testing (Exception: TradeGuard). Possible to join ITCH and AMD Multicasts and receive heartbeats. |
March 22 | 10:00-14:00 CET | Login | API login available |
March 23 | Testing not available | Testing not available | Testing not available |
March 24-28 | 12:00-18:00 CET | Telnet |
All protocols available for Telnet testing (Exception: TradeGuard). Possible to join ITCH and AMD Multicasts and receive heartbeats. |
March 29-30 | Testing not available | Testing not available | Testing not available |
Testing dates for April will be announced on March 28 at the latest.
New failover IPs for OMnet, Trayport, ITCH, AMD, GLIMPSE and TradeGuard are available in the Connectivity Guideline for Genium INET.
Customers using FIX ports have received a separate e-mail with new failover IP details. For questions, please contact MAC@nasdaq.com.
Test schedule – INET Nordic
Connectivity testing for INET Nordic will be available according to the following schedule:
Testing dates | Testing hours | Testing method | Comments |
March 3-7 | 07:00-22:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH and NLS Multicasts and receive heartbeats. |
March 8-9 | Testing not available | Testing not available | Testing not available |
March 10-14 | 07:00-22:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH and NLS Multicasts and receive heartbeats. |
March 15-16 | Testing not available | Testing not available | Testing not available |
March 17-21 | 07:00-22:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH and NLS Multicasts and receive heartbeats. |
March 22-23 | Testing not available | Testing not available | Testing not available |
March 24-28 | 07:00-22:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH and NLS Multicasts and receive heartbeats. |
March 29-30 | Testing not available | Testing not available | Testing not available |
Testing dates for April will be announced on March 28 at the latest.
New failover IPs for FIX, OUCH, associated Drops, GLIMPSE, ITCH (TCP) and NLS Re-request are available in the Member Portal.
New failover IPs for ITCH and NLS Multicast are available in the Connectivity Guideline for INET.
Test schedule – Nasdaq Derivatives Trading System (NDTS)
Connectivity testing for NDTS will be available according to the following schedule:
Testing dates | Testing hours | Testing method | Comments |
March 3 | Testing not available | Testing not available | Testing not available |
March 4-7 | 10:00-17:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH Multicasts and receive heartbeats. |
March 8-9 | Testing not available | Testing not available | Testing not available |
March 10-14 | 10:00-17:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH Multicasts and receive heartbeats. |
March 15-16 | Testing not available | Testing not available | Testing not available |
March 17-21 | 10:00-17:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH Multicasts and receive heartbeats. |
March 22-23 | Testing not available | Testing not available | Testing not available |
March 24-28 | 10:00-17:00 CET | Telnet |
All protocols available for Telnet testing. Possible to join ITCH Multicasts and receive heartbeats. |
March 29-30 | Testing not available | Testing not available | Testing not available |
Testing dates for April will be announced on March 28 at the latest.
New failover IPs for FIX, OUCH, associated Drops, GLIMPSE and ITCH Re-Request will be published in the Member Portal on March 4.
New failover IPs for ITCH and AMD Multicast are available in the Connectivity Guideline for NDTS.
Test schedule – Genium Consolidated Feed (GCF)
Connectivity testing for GCF will be available according to the following schedule:
Testing dates | Testing hours | Testing method | Comments |
March 3-7 | 09:00-17:30 CET | Telnet, Login |
TIP available. Feed contents: Basic data (until further notice, this data should not be treated/used as Production data) |
March 8-9 | 09:00-17:30 CET | Telnet, Login | Heartbeats only |
March 10-14 | 09:00-17:30 CET | Telnet, Login |
TIP available. Feed contents: Basic data (until further notice, this data should not be treated/used as Production data) |
March 15-16 | 09:00-17:30 CET | Telnet, Login | Heartbeats only |
March 17-21 | 09:00-17:30 CET | Telnet, Login |
TIP available. Feed contents: Basic data (until further notice, this data should not be treated/used as Production data) |
March 22-23 | 09:00-17:30 CET | Telnet, Login | Heartbeats only |
March 24-28 | 09:00-17:30 CET | Telnet, Login |
TIP available. Feed contents: Basic data (until further notice, this data should not be treated/used as Production data) |
March 29-30 | 09:00-17:30 CET | Telnet, Login | Heartbeats only |
Testing dates for April will be announced on March 28 at the latest.
New failover IP for GCF is available on the GCF webpage.
Communication
Updates regarding Nasdaq Secondary Data Center relocation will be provided primarily via IT Notices. Please ensure that you have signed up to the relevant “IT Information” channels on our Subscription service page to receive the latest information.
Please visit our relocation website for latest updates on this project: https://www.nasdaq.com/solutions/european-market-services/secondary-dc-relocation.
Contact
For user/account related questions, please contact:
Member & Account Configuration
MAC@nasdaq.com
For technical questions, please contact:
Exchange Services
EMO@nasdaq.com
+46 8 405 7700
For project related information, please contact:
Technical Relations
Riitta Pesiö
Best regards,
Nasdaq Nordic, Nasdaq Baltic, Nasdaq Clearing AB and Nasdaq CSD SE
Nasdaq Copenhagen, Nasdaq Helsinki, Nasdaq Iceland, Nasdaq Riga, Nasdaq Stockholm, Nasdaq Tallinn and Nasdaq Vilnius are respectively brand names for Nasdaq Copenhagen A/S, Nasdaq Helsinki Ltd, Nasdaq Iceland hf., Nasdaq Riga AS, Nasdaq Stockholm AB, Nasdaq Tallinn AS and AB Nasdaq Vilnius. Nasdaq Nordic represents the common offering by Nasdaq Copenhagen, Nasdaq Helsinki, Nasdaq Iceland and Nasdaq Stockholm. Nasdaq Baltic represents the common offering by Nasdaq Tallinn, Nasdaq Riga and Nasdaq Vilnius.